Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 4 | 4.000 | 0 | 0.000 | 0.000 |
45W26 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 2503/ (1) 2/06 -37 (प्रा0आ0)/ 06 दि0 20.9.06
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
194.40
Resanction Cost :
194.40
Tentative Cost :
194.40
Exp. Upto Last Fy : 190.48
For CFY 2024-2025
Remaining : 3.92
Demand : 3.92
Allotment : 3.92
Exp in CFY : 3.91
Total Up to Date Exp : 194.39
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
17 years 9 months ago
20 Sep 2006
Tentative Completion date:
3 months 3 weeks ago
20 Mar 2024
Actual Completion Date:
3 months 2 weeks ago
31 Mar 2024
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
WORK COMPLETED -- as on 22-Apr-2024