Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 0.000 | 7 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 36 | 36 | 0.000 | 36 | 0.000 | 0.000 |
45W274 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0- 2387/।।।(2)/16-09(एम0एल0ए0)/ 2016, दिनांक- 01.09.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
27.92
Resanction Cost :
27.92
Tentative Cost :
27.92
Exp. Upto Last Fy : 25.86
For CFY 2024-2025
Remaining : 2.06
Demand : 2.06
Allotment : 0.18
Exp in CFY : 0.18
Total Up to Date Exp : 26.04
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
7 years 10 months ago
01 Sep 2016
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Physical Peramenters