Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
45W276 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5729(1)/।।।(2)/21-09(एम0एल0ए0)/2017टी0सी0आई0वी0, दि0 30.11.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
389.22
Resanction Cost :
389.22
Tentative Cost :
389.22
Exp. Upto Last Fy : 379.20
For CFY 2024-2025
Remaining : 10.02
Demand : 3.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 379.20
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
30 Nov 2021
Tentative Completion date:
3 months 3 weeks ago
25 Mar 2024
Actual Completion Date:
3 months 3 weeks ago
25 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण।कार्य तीन वर्षीय अनुरक्षण के अन्तर्गत है। -- as on 04-May-2024