Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 3.000 | 1 | 1.000 | 0.000 |
45W282 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग, देहरादून के पत्रांक संख्या-895/07 याता0-पी0एम0जी0एस0वाई0-नि0 ।।।, दि0 16.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 112.31 Lacs
Resanction Cost : 112.31 Lacs
Exp. Upto Last Fy : 87.44 Lacs
For CFY 2024-2025
Remaining : 24.87 Lacs
Demand : 24.87 Lacs
Allotment : 24.87 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 87.44 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
1 month 4 days from now
24 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डब्लू0बी0एम0, क्षतिग्रस्त दीवारों, काॅजवे, पैरापेट एवं स्कपर का कार्य प्रगति पर। -- as on 22-Feb-2024
Physical Peramenters