Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 3.000 | 1 | 1.000 | 1.000 |
45W282 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग, देहरादून के पत्रांक संख्या-895/07 याता0-पी0एम0जी0एस0वाई0-नि0 ।।।, दि0 16.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
112.31
Resanction Cost :
112.31
Tentative Cost :
112.31
Exp. Upto Last Fy : 87.44
For CFY 2024-2025
Remaining : 24.87
Demand : 24.87
Allotment : 18.32
Exp in CFY : 18.32
Total Up to Date Exp : 105.76
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 weeks 2 days ago
24 Jun 2024
Actual Completion Date:
3 weeks 2 days ago
24 Jun 2024
Remark
Bottelneck: no issue
work completed -- as on 01-Jun-2024