Work Profile Report [45W283]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग, उत्तराखण्ड, देहरादून के पत्रांक संख्या-895/07 याता0-पी0एम0जी0एस0वाई0-नि0-।।।, दि0 16.05.2023
TS Amount (lakhs) : 189.94 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
189.94
Resanction Cost :
189.94
Tentative Cost :
179.93
Saving
10.01
Exp. Upto Last Fy :
80.28
For CFY 2024-2025
Remaining :
109.66
Demand :
99.65
Allotment :
84.31
Exp in CFY :
84.31
Total Up to Date Exp :
164.59
Work completed
Sanction on : 1 year 7 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
40 %
Up to Date :
100 %
Tentative Completion date on : 6 months 1 week ago
15 Jun 2024
Actual Completion Date : 6 months 1 week ago
15 Jun 2024
Physical Linear Components
Remark
Overall Saving 10.01 has been recorded as expected cost of work reduced from 189.94 to 179.93 . -- as on 10-Dec-2024