Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.16 | 7.16 | 2.000 | 5.16 | 5.160 | 0.000 |
45W283 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग, उत्तराखण्ड, देहरादून के पत्रांक संख्या-895/07 याता0-पी0एम0जी0एस0वाई0-नि0-।।।, दि0 16.05.2023
TS Amount (lakhs) : 189.94 Lacs
Financial Detail
Sanction Cost : 189.94 Lacs
Resanction Cost : 189.94 Lacs
Exp. Upto Last Fy : 80.28 Lacs
For CFY 2024-2025
Remaining : 109.66 Lacs
Demand : 109.66 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 80.28 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 50 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
1 month 3 weeks ago
26 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डब्लू0बी0एम0, क्षतिग्रस्त दीवारों,ं स्कपर ,सी0सी0 रोड व गैबियन्स का कार्य प्रगति पर। -- as on 22-Feb-2024
Physical Peramenters