Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 14.28 | 14.28 | 3.000 | 11.28 | 11.280 | 0.000 |
45W284 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग, उत्तराखण्ड, देहरादून के पत्रांक संख्या-895ध्07 याता0-पी0एम0जी0एस0वाई0-नि0-।।।, दि0 16.05.2023
TS Amount (lakhs) : 278.6 Lacs
Financial Detail
Sanction Cost : 278.60 Lacs
Resanction Cost : 278.60 Lacs
Exp. Upto Last Fy : 124.71 Lacs
For CFY 2024-2025
Remaining : 153.89 Lacs
Demand : 153.89 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 124.71 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
11 months 3 days ago
16 Jun 2023
Tentative Completion date:
1 month 3 weeks ago
23 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डब्लू0बी0एम0, क्षतिग्रस्त दीवारों, काॅजवे, व स्कपर का कार्य प्रगति पर। 2 कि0मी0 लम्बाई में पी0सी0 का कार्य पूर्ण शेष कार्य प्रगति पर। -- as on 22-Feb-2024
Physical Peramenters