Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.75 | 9.75 | 4.000 | 5.75 | 5.750 | 5.750 |
45W285 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग, उत्तराखण्ड, देहरादून के पत्रांक संख्या-895ध्07 याता0-पी0एम0जी0एस0वाई0-नि0-।।।, दि0 16.05.2023
TS Amount (lakhs) : 173.19 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
173.19
Resanction Cost :
173.19
Tentative Cost :
173.19
Exp. Upto Last Fy : 81.82
For CFY 2024-2025
Remaining : 91.37
Demand : 91.37
Allotment : 46.39
Exp in CFY : 46.39
Total Up to Date Exp : 128.21
Work completed
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 100 %
Sanction on :
1 year 1 month ago
16 Jun 2023
Tentative Completion date:
1 month 2 weeks ago
31 May 2024
Actual Completion Date:
1 month 2 weeks ago
30 May 2024
Remark
Bottelneck: no issue
Work completed -- as on 28-Jun-2024
Physical Peramenters