Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 4.500 | 1.5 | 1.500 | 1.500 |
45W286 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग, उत्तराखण्ड, देहरादून के पत्रांक संख्या-895ध्07 याता0-पी0एम0जी0एस0वाई0-नि0-।।।, दि0 16.05.2023
TS Amount (lakhs) : 163.47 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
163.47
Resanction Cost :
163.47
Tentative Cost :
163.47
Exp. Upto Last Fy : 93.58
For CFY 2024-2025
Remaining : 69.89
Demand : 69.89
Allotment : 33.86
Exp in CFY : 33.86
Total Up to Date Exp : 127.43
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
1 year 1 month ago
16 Jun 2023
Tentative Completion date:
3 months 2 days ago
15 Apr 2024
Actual Completion Date:
2 months 2 weeks ago
30 Apr 2024
Remark
Bottelneck: no issue
Work completed. -- as on 28-Jun-2024
Physical Peramenters