Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11.5 | 11.5 | 4.000 | 7.5 | 7.500 | 1.000 |
45W287 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग, उत्तराखण्ड, देहरादून के पत्रांक संख्या-895ध्07 याता0-पी0एम0जी0एस0वाई0-नि0-।।।, दि0 16.05.2023
TS Amount (lakhs) : 197.92 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
197.92
Resanction Cost :
197.92
Tentative Cost :
197.92
Exp. Upto Last Fy : 87.11
For CFY 2024-2025
Remaining : 110.81
Demand : 110.81
Allotment : 0.40
Exp in CFY : 0.40
Total Up to Date Exp : 87.52
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 75 %
Sanction on :
1 year 1 month ago
16 Jun 2023
Tentative Completion date:
1 month 1 week from now
30 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डब्लू0बी0एम0, क्षतिग्रस्त दीवारों एवं स्कपर का कार्य पूर्ण।6.5कि0मी0 लम्बाई में पी0सी0 का कार्य पूर्ण। कच्ची नाली व शेष पी0सी0 का कार्य प्रगति पर। -- as on 12-Jul-2024
Physical Peramenters