Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 30.5 | 30.5 | 0.000 | 30.5 | 0.000 | 0.000 |
45W310 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली सं0-49198,दि0-18.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
8.23
Resanction Cost :
8.23
Tentative Cost :
8.23
Exp. Upto Last Fy : 6.20
For CFY 2024-2025
Remaining : 2.03
Demand : 2.03
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 6.20
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
1 year 1 month ago
18 May 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Geotechnical investigation completed. Structural design in progress. -- as on 13-Jul-2024
Physical Peramenters