Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
45W315 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई पत्रावली सं0-33957, 160134/2023, दिनांक-10.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
405.99
Resanction Cost :
405.99
Tentative Cost :
405.99
Exp. Upto Last Fy : 58.72
For CFY 2024-2025
Remaining : 347.27
Demand : 335.82
Allotment : 86.11
Exp in CFY : 86.11
Total Up to Date Exp : 144.83
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 40 %
Sanction on :
9 months 1 week ago
10 Oct 2023
Tentative Completion date:
8 months 1 week from now
29 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Hill side cutting for Extra widening ,scupper, Walling and G1 and G2 work completed in 5 km length, coolie walling and other work in progress. -- as on 13-Jul-2024
Physical Peramenters