Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.4 | 1.4 | 0.000 | 1.4 | 1.400 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 72 | 72 | 0.000 | 72 | 0.000 | 0.000 |
45W323 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्रावली संख्या- 48510/09, दिनांक-01.02.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
50.38
Resanction Cost :
50.38
Tentative Cost :
50.38
Exp. Upto Last Fy : 10.33
For CFY 2024-2025
Remaining : 40.05
Demand : 40.05
Allotment : 30.00
Exp in CFY : 14.70
Total Up to Date Exp : 25.02
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 75 %
Sanction on :
5 months 2 weeks ago
01 Feb 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Hill side cutting work completed in 1 Km length. Protection work in progress. -- as on 13-Jul-2024