Work Profile Report [45W338]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : ई0-पत्रावली संख्या-68022/09, 188763/2024, दिनांक- 08.02.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
153.63
Resanction Cost :
153.63
Tentative Cost :
142.80
Saving
10.83
Exp. Upto Last Fy :
122.42
For CFY 2025-2026
Remaining :
31.21
Demand :
15.58
Allotment :
20.37
Exp in CFY :
20.37
Total Up to Date Exp :
142.80
Work completed
Sanction on : 1 year 6 months ago
08 Feb 2024
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
100 %
Tentative Completion date on : 1 month 1 week ago
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 10.83 has been recorded as expected cost of work reduced from 153.63 to 142.80 . -- as on 29-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: