Work Profile Report [45W41]

पोखार-गेंवली (भिंलग) मोटर मार्ग का नव निर्माण कार्य। (प्रथम चरण - 10 कि0मी0)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0- 2091/।।।(2)/16-44(प्रा0आ0)/ 2016, दिनांक- 26.07.2016

TS Amount (lakhs) : 51.4 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

51.40

Resanction Cost :

51.40

Tentative Cost :

15.00

Saving

36.40

Exp. Upto Last Fy :

14.98

For CFY 2025-2026

Remaining :

36.42

Demand :

0.00

Allotment :

0.06

Exp in CFY :

0.06

Total Up to Date Exp :

15.04

Work completed

Sanction on : 8 years 11 months ago

26 Jul 2016

Physical Progress:

At start of FY 2025-2026 :

95 %

Up to Date :

95 %

Tentative Completion date on : 3 months 1 week ago

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
10
0.000
10
0.000
0.000

Remark

view all

मुआवजा वितरण की कार्यवाही गतिमान। -- as on 26-Apr-2025

Rating : 95

Forest Case Pending At : 14: AIP Conservator

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand