Work Profile Report [45W41]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0- 2091/।।।(2)/16-44(प्रा0आ0)/ 2016, दिनांक- 26.07.2016
TS Amount (lakhs) : 51.4 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
51.40
Resanction Cost :
51.40
Tentative Cost :
20.00
Saving
31.40
Exp. Upto Last Fy :
14.98
For CFY 2025-2026
Remaining :
36.42
Demand :
5.02
Allotment :
0.06
Exp in CFY :
0.06
Total Up to Date Exp :
15.04
Work completed
Sanction on : 9 years 5 months ago
26 Jul 2016
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 2 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
शेष प्रतिकर वितरित किया जा रहा है। -- as on 01-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2026 PWD Uttarakhand