Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 14 | 14 | 0.000 | 14 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 72 | 72 | 0.000 | 72 | 0.000 | 0.000 |
45W42 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0- 2091/।।।(2)/16-44(प्रा0आ0)/ 2016, दिनांक- 26.07.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
52.02
Resanction Cost :
52.02
Tentative Cost :
52.02
Exp. Upto Last Fy : 0.59
For CFY 2024-2025
Remaining : 51.43
Demand : 15.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.59
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
7 years 11 months ago
27 Jul 2016
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण प्रस्ताव में कार्यालय अधीक्षण अभियन्ता, 8वाॅ वृृत्त, लो0नि0वि0, टिहरी द्वारा आपत्ति लगायी गयी जिनका निराकरण किया जा रहा है। -- as on 31-Jul-2020
Physical Peramenters