Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
45W43 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0- 2091/।।।(2)/16-44 (प्रा0आ0)/ 2016, दिनांक-26.07.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
6.18
Resanction Cost :
6.18
Tentative Cost :
6.18
Exp. Upto Last Fy : 1.20
For CFY 2024-2025
Remaining : 4.98
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.20
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
7 years 11 months ago
26 Jul 2016
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
उक्त मोटर मार्ग पुनः समरेखण विवाद किया जा रहा है। -- as on 31-Jan-2021
Physical Peramenters