Work Profile Report [45W65]

जगदी-बडियारगांव-तितराना-थार्ती मोटर मार्ग का नव निर्माण कार्य। (प्रथम चरण लं0- 7.00)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0- 2387/।।।(2)/16-09(एम0एल0ए0)/2016, दिनांक- 01.09.2016

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

29.93

Resanction Cost :

29.93

Tentative Cost :

29.93

Exp. Upto Last Fy :

0.35

For CFY 2025-2026

Remaining :

29.58

Demand :

0.50

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.35

Survey work done

Sanction on : 8 years 9 months ago

01 Sep 2016

Physical Progress:

At start of FY 2025-2026 :

20 %

Up to Date :

20 %

Tentative Completion date on : 3 months 2 days from now

30 Sep 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
7
7
7.000
0
0.000
0.000

Remark

view all

उक्त वनभूमि प्रस्ताव प्रमुख वन संरक्षक एवं नोडल अधिकारी, उत्तराखण्ड देहरादून के पत्रांक संख्या- 2895/12-1 देहरादून, दिनांक- 30.05.2025 द्वारा प्रमुख सचिव वन एवं पर्यावरण, उत्तराखण्ड शासन वन अनुभाग-3 को सैद्धान्तिक स्वीकृति प्राप्त करने हेतु प्रेषत किया है । -- as on 23-Jun-2025

Rating : 21

Forest Case Pending At : 08: State Government

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: