Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 60 | 60 | 0.000 | 60 | 0.000 | 0.000 |
45W66 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0- 2387/।।।(2)/16-09(एम0एल0ए0)/ 2016, दिनांक- 01.09.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
11.55
Resanction Cost :
11.55
Tentative Cost :
11.55
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 11.45
Demand : 11.45
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 15 %
Sanction on :
7 years 10 months ago
01 Sep 2016
Tentative Completion date:
4 months 1 week from now
30 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Hydrological and Geotechnical investigation of bridge in progress. -- as on 13-Jul-2024
Physical Peramenters