Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
46W203 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 4417/।।। (2)/15-4 (मं0मं0घो0)/2015 दिनांक 27 मई 2015
TS Amount (lakhs) : 58 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
58.00
Resanction Cost :
58.00
Tentative Cost :
58.00
Exp. Upto Last Fy : 20.56
For CFY 2024-2025
Remaining : 37.44
Demand : 8.15
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 20.56
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
9 years 1 month ago
27 May 2015
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रतिकर वितरण की कार्यवाही गतिमान है। द्वितीय चरण स्टेज-1 का कार्य प्रगति पर है। -- as on 10-Apr-2024
Physical Peramenters