Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.125 | 1.125 | 1.120 | 0.0049999999999999 | 0.000 | 0.000 |
46W588 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली संख्या-33542 लोक निर्माण अनुभाग-2 दिनाकं 12.05.2023
TS Amount (lakhs) : 39.79 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
39.79
Resanction Cost :
39.79
Tentative Cost :
39.79
Exp. Upto Last Fy : 31.36
For CFY 2024-2025
Remaining : 8.43
Demand : 13.00
Allotment : 2.56
Exp in CFY : 2.56
Total Up to Date Exp : 33.92
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
1 year 2 months ago
12 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 27-Mar-2024
Physical Peramenters