Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12.8 | 12.8 | 10.000 | 2.8 | 2.800 | 0.000 |
46W589 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग, उत्तराखण्ड, देहरादून के पत्रांक-895ध्07 याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 279.26 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
279.26
Resanction Cost :
279.26
Tentative Cost :
279.26
Exp. Upto Last Fy : 184.22
For CFY 2024-2025
Remaining : 95.04
Demand : 95.04
Allotment : 57.45
Exp in CFY : 57.44
Total Up to Date Exp : 241.66
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 months 4 hours ago
17 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व अवशेष। -- as on 15-Jun-2024
Physical Peramenters