Work Profile Report [46W600]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : ई पत्रावली संख्या-37809 लोक निर्माण अनुभाग-2 देहरादून दिनांक 03 अगस्त 2023
TS Amount (lakhs) : 159.48 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
159.48
Resanction Cost :
159.48
Tentative Cost :
159.48
Exp. Upto Last Fy :
62.25
For CFY 2024-2025
Remaining :
97.23
Demand :
92.71
Allotment :
66.92
Exp in CFY :
66.92
Total Up to Date Exp :
129.16
Work completed
Sanction on : 1 year 3 months ago
03 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
40 %
Up to Date :
100 %
Tentative Completion date on : 3 months 3 weeks ago
30 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व अवशेष। -- as on 16-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand