Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
46W600 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या-37809 लोक निर्माण अनुभाग-2 देहरादून दिनांक 03 अगस्त 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 159.48 Lacs
Resanction Cost : 159.48 Lacs
Exp. Upto Last Fy : 61.05 Lacs
For CFY 2024-2025
Remaining : 98.43 Lacs
Demand : 105.89 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 61.05 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
9 months 2 weeks ago
03 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 21-Dec-2023
Physical Peramenters