Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 3.000 | 2 | 2.000 | 0.000 |
46W601 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के ई पत्रावली संख्या-47979 लोक निर्माण अनुभाग-2 देहरादून दिनांक 29 अगस्त 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 180.70 Lacs
Resanction Cost : 180.70 Lacs
Exp. Upto Last Fy : 96.23 Lacs
For CFY 2024-2025
Remaining : 84.47 Lacs
Demand : 103.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 96.23 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 55 %
Sanction on :
8 months 2 weeks ago
29 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 02-Feb-2024
Physical Peramenters