Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.7 | 3.7 | 3.500 | 0.2 | 0.200 | 0.000 |
46W612 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली संख्या-24396 लोक निर्माण अनुभाग-2 दिनाकं 31.03.2023
TS Amount (lakhs) : 124.2 Lacs
Financial Detail
Sanction Cost : 124.20 Lacs
Resanction Cost : 124.20 Lacs
Exp. Upto Last Fy : 49.02 Lacs
For CFY 2024-2025
Remaining : 75.18 Lacs
Demand : 71.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 49.02 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
1 year 1 month ago
31 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 02-Feb-2024
Physical Peramenters