Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 27.75 | 27.75 | 0.000 | 27.75 | 27.750 | 0.000 |
46W673 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के पत्रांक-212/।।।(2)/2024-01 (प्रा0आ0)/2023 लोक निर्माण अनुभाग-2 देहरादून दिनांक 31 जनवरी, 2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
408.73
Resanction Cost :
408.73
Tentative Cost :
408.73
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 408.73
Demand : 408.73
Allotment : 51.94
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 07-Mar-2024
Physical Peramenters