Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 34.6 | 34.6 | 0.000 | 34.6 | 34.600 | 0.000 |
46W674 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के पत्रांक-212ध्।।।(2)ध्2024-01 (प्रा0आ0)ध्2023 लोक निर्माण अनुभाग-2 देहरादून दिनांक 31 जनवरी, 2024
TS Amount (lakhs) : 451.84 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
451.84
Resanction Cost :
451.84
Tentative Cost :
451.84
Exp. Upto Last Fy : 228.86
For CFY 2024-2025
Remaining : 222.98
Demand : 222.98
Allotment : 150.00
Exp in CFY : 115.58
Total Up to Date Exp : 344.43
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 07-Mar-2024
Physical Peramenters