Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11.3 | 11.3 | 0.000 | 11.3 | 5.000 | 0.000 |
46W677 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के ई पत्रावली संख्या-48456 लोक निर्माण अनुभाग-2 देहरादून दिनांक 07 मार्च 2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
221.70
Resanction Cost :
221.70
Tentative Cost :
221.70
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 221.70
Demand : 221.70
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 months 1 week ago
07 Mar 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अघीक्षण अभियन्ता 8 वाॅ वृत द्वारा निविदा आमंत्रित। अनुबन्ध गठित की अनुमानित तिथि 04 अगस्त 2024 -- as on 02-Jul-2024