Work Profile Report [47W122]

थाती डागर से रैंतासी तक मोटर मार्ग का नवनिर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 6276/।।।(2)/10-07(एम0एल0ए0) /2010 दि0 13 दिसम्बर, 2010

TS Amount (lakhs) : 50.4 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

50.40

Resanction Cost :

50.40

Tentative Cost :

50.40

Exp. Upto Last Fy :

34.56

For CFY 2024-2025

Remaining :

15.84

Demand :

5.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

34.56

Alignment Approved

Sanction on : 13 years 11 months ago

13 Dec 2010

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

70 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4
4
0.000
4
0.000
0.000

Remark

view all

एन0पी0वी0 एवं क्षतिपूरक वृक्षारोपण की धनराशि का ड़िमाण्ड़ नोट प्रभागीय वाधिकारी से प्राप्त। धनावंटन हेतु इस कार्यालय के पत्रांक 2089/33सी0 दिनांक 08.11.2024 द्वारा प्रमुख अभियन्ता एवं विभागाध्यक्ष महोदय लो0नि0वि0 देहरादून को पत्र प्रेषित किया गया है। -- as on 11-Nov-2024

Rating : 74

Forest Case Pending At : 11: AIP Division

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: