Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 9 | 9 | 9 | 0 |
47W127 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 1404/ंं(2)/11-08(प्रा0आ0)/2010 टी0सी0-1 दि0 22.03.2011
TS Amount (lakhs) : 0.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
0.41
Resanction Cost :
0.41
Tentative Cost :
0.41
Exp. Upto Last Fy : 0.01
For CFY 2024-2025
Remaining : 0.40
Demand : 0.41
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.01
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
13 years 3 months ago
22 Mar 2011
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
ग्राम वासिायें द्वारा उक्त कार्य हेतु सहमति प्राप्त नहीं हो पा रही है। -- as on 31-Jul-2020
Physical Peramenters