Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 0.000 | 8 | 0.000 | 0.000 |
47W189 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 549/।।।(2)/14-49(प्रा0आ0)/2013 दि0 29.01.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
67.44
Resanction Cost :
67.44
Tentative Cost :
67.44
Exp. Upto Last Fy : 20.07
For CFY 2024-2025
Remaining : 47.37
Demand : 5.00
Allotment : 5.00
Exp in CFY : 4.96
Total Up to Date Exp : 25.03
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 years 5 months ago
29 Jan 2014
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
उपखण्ड़ स्तर से काश्तकारों को भूमि अध्यापन हेतु प्रेषित किया गया है। काश्तकारों की रजिस्ट्री करने के उपरान्त ही काश्तकारों को प्रतिकर आवंटन करना सम्भव हो पायेगा -- as on 14-Jul-2024
Physical Peramenters