Work Profile Report [47W189]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0 549/।।।(2)/14-49(प्रा0आ0)/2013 दि0 29.01.2014
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
67.44
Resanction Cost :
67.44
Tentative Cost :
67.44
Exp. Upto Last Fy :
43.76
For CFY 2025-2026
Remaining :
23.68
Demand :
23.68
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
43.76
Work completed
Sanction on : 11 years 2 months ago
29 Jan 2014
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
100 %
Tentative Completion date on : 5 days 23 hours ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वनभूमि हस्तान्तरण की विधिवत स्वीकृति प्राप्त। -- as on 24-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: