Work Profile Report [47W189]

आमणी से गड़ाकोट तक मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0 सं0 549/।।।(2)/14-49(प्रा0आ0)/2013 दि0 29.01.2014

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

67.44

Resanction Cost :

67.44

Tentative Cost :

67.44

Exp. Upto Last Fy :

20.07

For CFY 2024-2025

Remaining :

47.37

Demand :

5.00

Allotment :

5.00

Exp in CFY :

4.96

Total Up to Date Exp :

25.03

Alignment Approved

Sanction on : 10 years 9 months ago

29 Jan 2014

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

90 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
8
8
0.000
8
0.000
0.000

Remark

view all

पहाड़ कटान का कार्य पूर्ण। मुआवजा वितरण की कार्यवाही गतिमान है। -- as on 05-Nov-2024

Rating : 96

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand