Work Profile Report [47W190]

कोठार लिंक हल्का वाहन मार्ग का मोटर मार्ग में परिवर्तन एवं डामरीकरण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0 सं0 549/।।।(2)/14-49(प्रा0आ0)/2013 दि0 29.01.2014

TS Amount (lakhs) : 5.66 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

5.66

Resanction Cost :

5.66

Tentative Cost :

5.66

Exp. Upto Last Fy :

5.16

For CFY 2025-2026

Remaining :

0.50

Demand :

0.24

Allotment :

0.24

Exp in CFY :

0.24

Total Up to Date Exp :

5.41

Work completed

Sanction on : 11 years 11 months ago

29 Jan 2014

Physical Progress:

At start of FY 2025-2026 :

95 %

Up to Date :

100 %

Tentative Completion date on : 9 months 3 weeks ago

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
4.3
4.3
0.000
4.3
4.300
4.300

Remark

view all

मार्ग का डामरीकरण का कार्य पूर्ण हो चुका है। -- as on 14-Jan-2026

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck