Work Profile Report [47W194]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0 549/।।।(2)/14-49(प्रा0आ0)/2013 दि0 29.01.2014
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
55.36
Resanction Cost :
55.36
Tentative Cost :
55.36
Exp. Upto Last Fy :
26.24
For CFY 2025-2026
Remaining :
29.12
Demand :
18.32
Allotment :
20.00
Exp in CFY :
9.57
Total Up to Date Exp :
35.81
Alignment Approved
Sanction on : 11 years 10 months ago
29 Jan 2014
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
50 %
Tentative Completion date on : 3 months 2 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वनभूमि प्रस्ताव गठित किया जा रहा है। -- as on 09-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: