Work Profile Report [47W194]

डडुवा से सिरोला होतं हुये मयाली पाटाखाल तक मोटर मार्ग का पुल सहित नवनिर्माण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0 सं0 549/।।।(2)/14-49(प्रा0आ0)/2013 दि0 29.01.2014

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

55.36

Resanction Cost :

55.36

Tentative Cost :

55.36

Exp. Upto Last Fy :

26.24

For CFY 2025-2026

Remaining :

29.12

Demand :

29.12

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

26.24

Alignment Approved

Sanction on : 11 years 2 months ago

29 Jan 2014

Physical Progress:

At start of FY 2025-2026 :

0 %

Up to Date :

50 %

Tentative Completion date on : 11 months 3 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
7
6.6
0.000
6.6
6.600
0.000

Remark

view all

एन0पी0वी0 की बढ़ी धनराशि कैम्पा मद में जमा की जा चुकी है एवं अनुपालन आख्या की सूचना इस कार्यालय के पत्रांक 2095/33सी0 दिनांक 11.11.2024 द्वारा प्रभागीय वनाधिकारी नरेन्द्रनगर वन प्रभाग मुनिकीरेती को प्रेषित की जा चुकी है। -- as on 11-Nov-2024

Rating : 60

Forest Case Pending At : 13: AIP DFO

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: