Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.5 | 3.52 | 3.52 | 0 |
47W200 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 549/।।।(2)/14-49(प्रा0आ0)/2013 दि0 29.01.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 34.97 Lacs
Resanction Cost : 34.97 Lacs
Exp. Upto Last Fy : 13.24 Lacs
For CFY 2024-2025
Remaining : 21.73 Lacs
Demand : 3.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 13.24 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 years 3 months ago
29 Jan 2014
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण हेतु अनुबंन्ध गठन की कार्यवाही गतिमान है। -- as on 14-May-2024