Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.5 | 0 |
47W205 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0 सं0 1144/।।।(2)/14-72(प्रा0आ0)/2013 दि0 04.03.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
11.67
Resanction Cost :
11.67
Tentative Cost :
11.67
Exp. Upto Last Fy : 2.45
For CFY 2024-2025
Remaining : 9.22
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.45
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
10 years 4 months ago
04 Mar 2014
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 17: AIP Govt of India
Bottelneck: no issue
अपर पमुख वन संरक्षक एवं नोड़ल अधिकारी देहरादून द्वारा आॅन लाईन कम्प्लाईन्स दिनांक 12-05-2023 को सत्यापित की जा चुकी है। -- as on 01-May-2024
Physical Peramenters