Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 5 | 5 | 0 |
47W263 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1152/।।।(2)/16-56(प्रा0आ0)/2015 टी0सी0 दि0 29.02.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 42.80 Lacs
Resanction Cost : 42.80 Lacs
Exp. Upto Last Fy : 20.30 Lacs
For CFY 2024-2025
Remaining : 22.50 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 20.30 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 years 2 months ago
29 Feb 2016
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 17: AIP Govt of India
Bottelneck: no issue
भूमि प्रतिकर गठित किया जा रहा है। द्वितीय चरण की स्वीकृति प्राप्त कार्य प्रगति पर है। -- as on 14-May-2024
Physical Peramenters