Work Profile Report [47W270]

पौड़ीखाल भासौं मिसिंग लिंक मोटर मार्ग का नव निर्माण (प्रथम चरण)

    Tenders

    Aggrements

    Project Activities

    alerts

    Samples

Administrative Approval Detail : श्शा0स0 1836/।।।(2)/18-10(एम.एल.ए.)/2016 दि0 13.07.2016

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

20.50

Resanction Cost :

20.50

Tentative Cost :

20.50

Exp. Upto Last Fy :

17.16

For CFY 2025-2026

Remaining :

3.34

Demand :

3.34

Allotment :

0.59

Exp in CFY :

0.00

Total Up to Date Exp :

17.16

Alignment Approved

Sanction on : 9 years 1 month ago

13 Jul 2016

Physical Progress:

At start of FY 2025-2026 :

70 %

Up to Date :

70 %

Tentative Completion date on : 6 months 3 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
2.5
2.12
0.000
2.12
2.120
0.000

Remark

view all

अनुपालन आख्या दिनांक 12.04.2024 को आॅन लाईन अपलोड़ की गयी थी जो कि वर्तमान तक नोड़ल अधिकारी स्तर पर लम्बित है। -- as on 03-Sep-2025

Rating : 101

Forest Case Pending At : 15: AIP Nodal

Hindrance / Bottleneck : Long Term Forest Approval