Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.12 | 2.12 | 0 |
47W270 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0स0 1836/।।।(2)/18-10(एम.एल.ए.)/2016 दि0 13.07.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 20.50 Lacs
Resanction Cost : 20.50 Lacs
Exp. Upto Last Fy : 13.67 Lacs
For CFY 2024-2025
Remaining : 6.83 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 13.67 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
7 years 10 months ago
13 Jul 2016
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
मार्ग पर स्ैद्धान्तिका स्वीकृति वन एवं पर्यावरण मंत्रालय -4 उत्तराखण्ड़ शासन के पत्रांक 634/(108)/2018 दिनांक 06.07.2018 द्वारा प्राप्त है। रिक्त पड़े स्थानों पर वृक्षारोपण एवं एन0पी0वी0 की धनराशि रूव0 1499549.00 दिनांक 26.11.2018 को आॅनलाइन कैम्पा मद में जमा की गयी है। अनुपालन आख्या इस कार्यालय के पत्रांक 2653/33सी0 दिनांक 01.12.2018 द्वारा प्रभागीय वनाधिकारी टिहरी कोे प्रेषित है। प्रभागीय वनाधिकारी टिहरी द्वारा अपने पत्रांक 3023/12-1 दिनांक 20.12.2018 द्वारा अनुपालन आख्या नोड़ल अधिकारी को प्रेषित किया गया है। पुनः अनुस्मारक इस कार्यालय के पत्रांक 115/33सीव0 दिनांक 19.01.2021 द्वारा अपर प्रमुुख वन संरक्षक नोडल अधिकारी देहरादून केा विधिवत स्वीकृति हेतु लिखा गया है। -- as on 14-May-2024
Physical Peramenters