Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 4.12 | 4.12 | 0 |
47W271 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0स0 1836/।।।(2)/18-10(एम.एल.ए.)/2016 दि0 13.07.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 27.07 Lacs
Resanction Cost : 27.07 Lacs
Exp. Upto Last Fy : 12.36 Lacs
For CFY 2024-2025
Remaining : 14.71 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 12.36 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
7 years 10 months ago
13 Jul 2016
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 14-May-2024
Physical Peramenters