Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Buildings | 2 | 2 | 2 | 0 |
47W288 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पुनरीक्षित स्वीकृति शा0स0 3243/।।।(2)/16-10(एम0एल0ए0)/2016 टी0सी0 दिनांक 28.12.2016
TS Amount (lakhs) : 143.69 Lacs
Financial Detail
Sanction Cost : 75.82 Lacs
Resanction Cost : 143.69 Lacs
Exp. Upto Last Fy : 125.35 Lacs
For CFY 2024-2025
Remaining : 18.34 Lacs
Demand : 18.34 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 125.35 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
7 years 4 months ago
28 Dec 2016
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 25-Oct-2023
Physical Peramenters