Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 1.25 | 1.25 | 0 |
47W297 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0सं0 2331/।।।(2)/16-10(एम.एल.ए.)/2016 दि0 17.08.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 7.76 Lacs
Resanction Cost : 7.76 Lacs
Exp. Upto Last Fy : 5.24 Lacs
For CFY 2024-2025
Remaining : 2.52 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 5.24 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
7 years 9 months ago
17 Aug 2016
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण प्रस्ताव गठित करने के उपरान्त अधीक्षण अभियन्ता 8वां वृत्त लो0नि0वि0 नई टिहरी के पत्रांक 5143/578 यातायात-8/2017 दिनंाक 09.09.2017 द्वारा अनुमोदित। अनुमोदित समरेखण पर कुछ ग्रामीणों द्वारा विवाद किया जा रहा है सुलझाने के प्रयास किये जा रहे है। -- as on 14-May-2024
Physical Peramenters