Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 2.22 | 2.22 | 0 |
47W299 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0सं0 2331/।।।(2)/16-10(एम.एल.ए.)/2016 दि0 17.08.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 30.00 Lacs
Resanction Cost : 30.00 Lacs
Exp. Upto Last Fy : 0.37 Lacs
For CFY 2024-2025
Remaining : 29.63 Lacs
Demand : 4.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.37 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
7 years 9 months ago
17 Aug 2016
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status ---
Bottelneck: no issue
वनभूमि हस्तान्तरण प्रस्ताव इस कार्यालय के पत्रांक..../6सी0 दिनांक 07.09.2021 द्वारा प्रभागीय वनाधिकारी नई टिहरी को प्रेषित। -- as on 15-Mar-2023
Physical Peramenters