Work Profile Report [47W33]

काण्डीखाल चन्द्रबदनी मोटर मार्ग का विस्तार मा0मु0घो0 सं0 73/2017 दिनांक 04.06.2017
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0स0 764/111-(2)/08-65 (प्रा0 आ0)/2007 दि0 24.03.08

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

280.00

Resanction Cost :

10.40

Tentative Cost :

10.40

Exp. Upto Last Fy :

7.19

For CFY 2024-2025

Remaining :

3.21

Demand :

3.20

Allotment :

3.50

Exp in CFY :

3.20

Total Up to Date Exp :

10.39

Alignment Approved

Sanction on : 16 years 7 months ago

24 Mar 2008

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

5 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
8
8
0.000
8
0.000
0.000

Remark

view all

Overall Saving 269.6 has been recorded as expected cost of work reduced from 280 to 10.4 . -- as on 16-Nov-2024

Rating : 5

Forest Case Pending At : 01: Withdraw

Hindrance / Bottleneck : To Cancel

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand