Work Profile Report [47W330]

डाण्डा भैंसकोट मोटर मार्ग का सिटूली डोब होते हुये ललूड़ीखाल-उनाना मोटर मार्ग तक विस्तार का कार्य (प्रथम चरण) मा0मु0घो0 सं0 496/2017 दिनांक 17.08.2017
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0 382/।।।(2)/17-10(एम0एल0ए0)/2017 दिनंाक 01.08.2017

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

17.55

Resanction Cost :

17.55

Tentative Cost :

17.55

Exp. Upto Last Fy :

11.17

For CFY 2024-2025

Remaining :

6.38

Demand :

2.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

11.17

Alignment Approved

Sanction on : 7 years 3 months ago

01 Aug 2017

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

90 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
3.05
0.000
3.05
3.050
0.000

Remark

view all

अधिकतर काश्तकारों को भूमि प्रतिकर आवंटित कर दिया गया है। शेष प्रतिकर हेतु काश्तकारों को सूचित कर दिया गया है। कास्तकारों के उपस्थित न होने के कारण प्रतिकर वितरित नही किया जा सका।काश्तकारों की उपस्थिति होने के उपरान्त ही अवशेष धनावंटन किया जाना सम्भव हो पायेगा। -- as on 21-Oct-2024

Rating : 99

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: