Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2.22 | 2.22 | 0 |
47W34 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 546/।।।(2)/09-53 (प्रा0आ0)/08 दि0 01.02.2009
TS Amount (lakhs) : 70 Lacs
Financial Detail
Sanction Cost : 70.00 Lacs
Resanction Cost : 70.00 Lacs
Exp. Upto Last Fy : 58.63 Lacs
For CFY 2024-2025
Remaining : 11.37 Lacs
Demand : 11.50 Lacs
Allotment : 5.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 58.63 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
15 years 3 months ago
01 Feb 2009
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष। -- as on 15-May-2024
Physical Peramenters