Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
47W353 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 342/।।।(2)/18-10(एम0एल0ए0)/2017 दिनांक 17.07.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 17.70 Lacs
Resanction Cost : 17.70 Lacs
Exp. Upto Last Fy : 4.41 Lacs
For CFY 2024-2025
Remaining : 13.29 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 4.41 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 years 10 months ago
17 Jul 2018
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
मार्ग पर वृक्षों की संख्या अधिक होने के कारण पुनः वृक्षों की गणना की गई है। वन भूमि हस्तान्तरण प्रस्ताव पुनः गठन की कार्यवाही गतिमान है। -- as on 01-May-2024
Physical Peramenters