Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
47W354 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 342/।।।(2)/18-10(एम0एल0ए0)/2017 दिनांक 17.07.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
16.08
Resanction Cost :
16.08
Tentative Cost :
16.08
Exp. Upto Last Fy : 3.85
For CFY 2024-2025
Remaining : 12.23
Demand : 4.00
Allotment : 0.50
Exp in CFY : 0.33
Total Up to Date Exp : 4.18
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 years 5 hours ago
17 Jul 2018
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
प्रस्ताव विधिवत स्वीकृति प्राप्त। -- as on 14-Jul-2024
Physical Peramenters