Work Profile Report [47W365]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश सं0 8112/।।।(2)/18-10(एम0एल0ए0)/2017 ई0सी0 दिनांक 31.12.2018
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
48.80
Resanction Cost :
48.80
Tentative Cost :
48.80
Exp. Upto Last Fy :
48.76
For CFY 2025-2026
Remaining :
0.04
Demand :
0.00
Allotment :
0.05
Exp in CFY :
0.05
Total Up to Date Exp :
48.81
Alignment Approved
Sanction on : 6 years 6 months ago
31 Dec 2018
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on : 4 weeks 15 hours from now
31 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वनभूमि हस्तान्तरण की विधिवत स्वीकृति प्राप्त हो चुकी है । -- as on 04-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: