Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 |
47W365 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 8112/।।।(2)/18-10(एम0एल0ए0)/2017 ई0सी0 दिनांक 31.12.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
48.80
Resanction Cost :
48.80
Tentative Cost :
0.00
Saving
48.80
Exp. Upto Last Fy : 36.15
For CFY 2024-2025
Remaining : 12.65
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 36.15
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 80 %
Sanction on :
5 years 6 months ago
31 Dec 2018
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 17: AIP Govt of India
Bottelneck: no issue
द्वितीय चरण का कार्य प्रगति पर है। -- as on 15-Jul-2024
Physical Peramenters