Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
47W378 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2277/।।।(2)/19-10(एम0एल0ए0)/2017 टी0सी0 दिनांक 21.06.2019
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 13.04 Lacs
Resanction Cost : 13.04 Lacs
Exp. Upto Last Fy : 0.59 Lacs
For CFY 2024-2025
Remaining : 12.45 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.59 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 years 10 months ago
21 Jun 2019
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: no issue
उक्त वन भूमि प्रस्ताव जिलाधिकरी स्तर पर लम्बित है। -- as on 01-May-2024
Physical Peramenters