Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
47W378 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2277/।।।(2)/19-10(एम0एल0ए0)/2017 टी0सी0 दिनांक 21.06.2019
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
13.04
Resanction Cost :
13.04
Tentative Cost :
13.04
Exp. Upto Last Fy : 0.59
For CFY 2024-2025
Remaining : 12.45
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.59
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
5 years 3 weeks ago
21 Jun 2019
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 07: Nodal
Bottelneck: no issue
आरक्षित वन भूमि पर वनीकरण हेतु स्थल चयन के उपरान्त मानचित्र एवं के0एम0एल0 हेतु इस कार्यालय के द्वारा आई0टी0जी0सी0 को पत्र प्रेषित किया गया है। 0 -- as on 15-Jul-2024
Physical Peramenters