Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.500 | 0.000 |
47W439 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 908(1)/।।।(2)/21-16(प्रा0आ0)/2015 दिनांक 30.03.2021
TS Amount (lakhs) : 103.17 Lacs
Financial Detail
Sanction Cost : 103.17 Lacs
Resanction Cost : 103.17 Lacs
Exp. Upto Last Fy : 84.24 Lacs
For CFY 2024-2025
Remaining : 18.93 Lacs
Demand : 18.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 84.24 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
3 years 1 month ago
30 Mar 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
4.50 किवमी0 लम्बाई तक कार्य पूर्ण। शेेष कार्य प्रगति पर हैं। -- as on 15-May-2024
Physical Peramenters