Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.6 | 3.6 | 3.6 | 0 |
47W440 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1336(1)/।।।(2)/21-10(एम.एल.ए.)/ 2017 टी.सी.-। दि0 11.05.2021
TS Amount (lakhs) : 88.15 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
88.15
Resanction Cost :
88.15
Tentative Cost :
88.15
Exp. Upto Last Fy : 85.33
For CFY 2024-2025
Remaining : 2.82
Demand : 2.80
Allotment : 2.80
Exp in CFY : 0.00
Total Up to Date Exp : 85.33
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 2 months ago
11 May 2021
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण । दायित्व शेष। -- as on 15-May-2024
Physical Peramenters