Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.6 | 3.6 | 3.6 | 0 |
47W440 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1336(1)/।।।(2)/21-10(एम.एल.ए.)/ 2017 टी.सी.-। दि0 11.05.2021
TS Amount (lakhs) : 88.15 Lacs
Financial Detail
Sanction Cost : 88.15 Lacs
Resanction Cost : 88.15 Lacs
Exp. Upto Last Fy : 85.33 Lacs
For CFY 2024-2025
Remaining : 2.82 Lacs
Demand : 2.80 Lacs
Allotment : 2.80 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 85.33 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 1 week ago
11 May 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण । दायित्व शेष। -- as on 15-May-2024
Physical Peramenters