Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.500 | 0.000 |
47W441 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1338/।।।(2)/21-10(एम.एल.ए.)/ 2017 टी.सी-।।।. दि0 11.05.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 130.99 Lacs
Resanction Cost : 130.99 Lacs
Exp. Upto Last Fy : 126.21 Lacs
For CFY 2024-2025
Remaining : 4.78 Lacs
Demand : 4.78 Lacs
Allotment : 2.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 126.21 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
3 years 1 week ago
11 May 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3 कि0मी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण शेष कार्य प्रगति पर है । -- as on 27-Oct-2023
Physical Peramenters